EnBW Inagurates 5MW Hydropower-Fed Hydrogen Plant in Wyhlen

Author:

FuelCellsWorks


  • Plant with five megawatts of electrical power complements the existing hydrogen production
  • Reallabor combines technical research with experience for commercial operations
  • Hydrogen as a contribution to climate protection and value creation

 

EnBW Energie Baden-Württemberg AG (EnBW) and naturenergie hochrhein AG (naturenergie) have inaugurated another plant for the production of hydrogen in the research project Reallabor H2-Wyhlen. The expansion has an electrical output of five megawatts (MW) and complements the existing 1 MW plant. The site thus has one of the largest production capacities for hydrogen in southern Germany. Both plants generate hydrogen with electricity from the neighboring hydroelectric power plant and are to supply industrial and mobility customers in the region in the future.

 

 “Hydrogen is an important building block for an energy system with a high proportion of renewable energies. EnBW already relies on flexible, hydrogen-capable power plants for this purpose. In the future, these will complement renewables and thus secure the power supply even in the dark and in the dark," says Prof. Dr. Wolfram Münch, Head of Research and Development at EnBW. “Together with natural energy and our research partners, we have built up valuable knowledge to accelerate the ramp-up of the hydrogen economy and to advance the use of technology on an industrial scale.”

 

New technology complements best practice

 

Klaus Müller, Member of the Board of Management of Naturenergie, adds: “Thanks to the existing infrastructure and the short distances between hydropower plant, hydrogen production, storage and grids, we have ideal conditions in Wyhlen to further develop the entire process chain in interaction. With the Reallabor, we gain important experience for large-format hydrogen operation and create the basis for the commercial operation of the plant.”

 

Technically, the existing and new buildings work on the same principle: In the so-called electrolysis, water is split into hydrogen and oxygen with the help of electricity. In the company, however, there is a difference. While the older electrolyzer is designed for uniform continuous operation, the new one can be quickly up and down. In this way, he can flexibly adapt his production to the respective electricity supply. This is an advantage especially where the generation of wind and sun fluctuates due to weather conditions.

 

Federal Government supports real laboratory with 15 million euros

 

In the H2-Wyhlen real laboratory, EnBW and naturenergie have been investigating together with research partners since 2021 how hydrogen can be produced efficiently and what is important during ongoing operation. The Federal Ministry for Economic Affairs and Energy (BMWE) has the project in the program “Real Laboratories of the Energy Transition” with 15 million euros (Mio. Euro) supported. About 9 million The extension is due to the euro.

 

“Hydrogen is a key building block for climate neutrality, competitiveness and industrial value creation. We need hydrogen for the success of the energy transition and for more resilience. That is why it is crucial that we accelerate the hydrogen ramp-up by improving funding and financing conditions, simplifying regulation and supporting leading markets," says Rita Schwarzelühr-Sutter, Parliamentary State Secretary in the Federal Environment Ministry and a member of the Bundestag from the Waldshut constituency. “This project is a good example of how companies contribute to the success of the energy transition with their innovations. That is why the federal government is also supporting with funding here. We also create planning security, for example with a hydrogen quota in transport.”

 

At the end of July, the new electrolyzer produced hydrogen for the first time. Currently, under real operating conditions, further plant parts such as gas treatment, compressors and storage systems are being gradually tested and ramped up. The expansion of the plant includes new stationary storage for up to 3.8 tonnes of hydrogen. The storage capacity thus rises to around 5 tonnes. In addition to the three existing filling stations, four new ones are added, at which the hydrogen is filled into pressure vessels on trucks.

 

The technical commissioning is to be completed by the end of the year. After a trial operation, the natural energy takes over the commercial operation. At the beginning, the real laboratory H2-Wyhlen also ends.

 

The new hydrogen plant is an important part of the site development, in which natural energy expands the site of the hydroelectric power plant to the natural energy campus Wyhlen – with a heating center, photovoltaic systems and a new main building with office, operating and event rooms.


H2 elections in number

  • Location: Grenzach-Wyhlen hydroelectric power plant
  • Power: new PEM electrolyzer with 5 MW, existing system with 1 MW alkaline electrolyzer
  • Power supply: hydropower from the Wyhlen run-of-river power plant (38.5 MW capacity)
  • Start of construction: second quarter of 2024
  • Inauguration: 1. October 2026
  • Commercial operation: early 2027
  • Use: Hydrogen is intended to supply industrial and mobility customers in the border region of Germany, Switzerland and France
  • Stationary storage capacity: around 5.1 tonnes
  • Filling stations: seven filling stations with different pressure levels
  • Total project costs: around 40 million euros; BMWE funding around 15 million euros
  • Future operator of the new plant: naturenergie hochrhein AG
  • Status: technical commissioning, trial operation is imminent

 

About the Reallabor H 2 -Wyhlen

 

The Reallabor H 2 -Wyhlen is one of the winning projects in the BMWE ideas competition “Reallabore der Energiewende” and was funded with around 15 million euros. Since 2021, naturenergie hochrhein AG (naturenergie) and EnBW Energie Baden-Württemberg AG (EnBW) have been conducting research together with the Center for Solar Energy and Hydrogen Research Baden-Württemberg (ZSW), the Holzapfel Group and Dialogik gGmbH on the efficient production of hydrogen from electrolysis with electricity from hydropower. EnBW has taken over the overall project management in the real laboratory and coordinated the research. The natural energy system operates the hydroelectric power plant, the existing hydrogen plant and, in the future, also the new hydrogen plant. The completion of the research project is another building block in the development of the area into the natural energy campus Wyhlen. In addition to an already completed heating center and photovoltaic systems, a new main building with office, operating and event rooms is also being built there. 

About EnBW Energie Baden-Württemberg AG

 

With around 31,500 employees, EnBW is one of the largest energy companies in Germany and Europe. It supplies energy to around 5.5 million customers and is active at all stages of value creation, from production to trade to grid operation and the distribution of electricity, heat and gas. In the course of the realignment from a classic energy supplier to a sustainable infrastructure company, the expansion of the distribution and transport networks for electricity, gas and hydrogen as well as renewable energies are key points of the EnBW growth strategy and the focus of the investments. By 2030, EnBW plans to invest up to 50 billion euros, around 85 percent of it in Germany. By then, around 80 percent of the EnBW generation portfolio will consist of renewable energy. These are key milestones on the road to the net zero target for the company's own greenhouse gas emissions in 2040. enbw.com

 

 

About naturenergie hochrhein AG

 

naturenergie hochrhein AG is a German-Swiss company headquartered in Rheinfelden, which, as a regional partner, enables people, municipalities and companies to live and live sustainably in southern Baden and Switzerland. With holistic energy solutions, the company is designing the framework conditions for the transformation of the energy system. It generates and distributes renewable energy from hydro and solar power. The origin of the electricity is documented by appropriate proofs of origin. The product and service portfolio covers the areas of photovoltaics, heat, construction and housing as well as electromobility. naturenergie hochrhein AG is part of naturenergie holding AG, which generated sales of 1.6 billion euros in 2025 with almost 1,500 employees. It is an investment company of EnBW Energie Baden-Württemberg AG. naturenergie.de

 

Source:FuelCellsWorks

Hot News

FuelCellChina Interviews