17
2026
-
11
Hy2gen Finalises €139.8M Hydrogen Bank Subsidy for 100MW Albatros Project
Author:
FuelCellsWorks
Danish electrolyser development moves closer to a 2028 final investment decision, with operations planned from 2031 and pipeline exports to Germany via the future Danish Hydrogen Backbone
Hy2gen Nordic AS has finalised a €139.8 million [approx. USD $151.3 million] European Hydrogen Bank funding commitment for its Albatros project — a 100 MW electrolyser plant in Kassø, Denmark, targeting 14,400 tonnes of renewable hydrogen per year for German industrial customers.
The project bid €0.97/kg in the EHB’s competitive auction, with construction planned from 2028 and operations from 2031, exporting hydrogen to Germany via the future Danish-German Hydrogen Backbone pipeline.
Albatros is a planned 100 MW PEM electrolyser plant located in Kassø, Aabenraa Municipality in southern Denmark. It will produce RFNBO-certified renewable hydrogen — meaning production meets the EU’s Renewable Fuels of Non-Biological Origin criteria, which qualifies it for use toward mandatory industrial and transport sub-quotas under the EU’s revised Renewable Energy Directive (RED III).
The plant is developed by Hy2gen Nordic AS, a subsidiary of the German-founded green hydrogen developer Hy2gen. The European Hydrogen Bank funding commitment of €139.8 million [approx. USD $151.3 million] covers the first ten years of operation.
The Competitive Auction Bid
The EHB funding was secured through a competitive auction process. Albatros won with a bid of €0.97/kg — the fixed premium per kilogram of hydrogen produced that the project will receive on top of market revenues over the support period. At projected output of approximately 14,400 tonnes per year, the total support across the commitment period amounts to around €139.8 million.
Kassø is well-positioned for a project of this kind. The area in southern Jutland has established wind energy infrastructure and grid connections, and sits close to the planned route of the Danish-German Hydrogen Backbone — the cross-border pipeline that will form the core of Northwest European hydrogen transport infrastructure.
German Industrial Customers Are the Target Market
The hydrogen produced at Albatros is not intended for the Danish market. It is earmarked for German industrial offtakers — specifically those needing to meet their RFNBO sub-quota obligations under RED III. The pipeline route via the Danish-German Hydrogen Backbone provides the physical connection. No specific offtake agreements have been named publicly.
Hege Økland, Managing Director of Hy2gen Nordic AS, said: “Albatros is the right project to address the increasing demand for renewable hydrogen in Germany.”
Timeline and Jobs
Construction is planned to begin in 2028, following a final investment decision. Operations are scheduled to start in 2031. The project is expected to create up to 500 construction jobs and 30 to 40 permanent positions once operational.